Phase 4 Sequence

The 72-hour activity sequence for the Prototype phase.

Updated

Prototyping gets an extra day because:

  • You can’t hand something across a table to the person next to you
  • Stitching requires waiting for others to finish their sections
  • Time zones mean a handoff might take 12 hours instead of 12 seconds
  • Building something realistic just takes focused time

Hour 0: AI opens Phase 4. Posts storyboard recap. Assigns roles and storyboard sections.

Hour 0-48: BUILDING — Makers build, Writer writes, Asset Collector gathers. Interviewer writes interview script. AI coordinates progress in #sprint-prototype.

Hour 48: Deadline for individual sections. Stitcher begins assembly.

Hour 56: Stitcher posts assembled prototype. ACTIVITY: Trial run (sync or async review).

Hour 60: Feedback incorporated. Final fixes.

Hour 66: Prototype locked. No more changes.

Hour 72: Phase 4 closes. Customers confirmed for Phase 5.