Timeline Planning

Set sprint dates, sync windows, customer interview slots, and time zone expectations.

Updated

Before the sprint, set concrete dates:

Day 0: Challenge Brief distributed to team Day 1-2: Phase 1 — Understand (48h window) Day 3-4: Phase 2 — Diverge (48h window) Day 5-6: Phase 3 — Decide (48h window) Day 7-9: Phase 4 — Prototype (72h window) Day 10-11: Phase 5 — Test (48h window)

Also schedule:

  • Customer recruiting starts Day 0 (same person as in original sprint)
  • Sync windows pinned to the team’s time zone overlap (if any)
  • Customer interview slots during Phase 5

Time Zone Considerations

  • All phase deadlines are in UTC
  • The AI converts to each person’s local time in reminders
  • Sync windows should be scheduled in the overlap between the earliest and latest time zones on the team
  • If there’s no viable overlap: skip sync windows entirely, use recorded walkthroughs instead